Which estimating method uses statistical data and historical information to predict future project costs?

a) Analogous estimating
b) Parametric estimating
c) Three-point estimating
d) Bottom-up estimating

View Answer

Answer: b) Parametric estimating
Explanation: Parametric estimating uses statistical relationships between historical data and project variables to predict future costs.

What is the purpose of a “bid bond” in the estimating and bidding process?

a) To guarantee that the project will be completed on time
b) To ensure the lowest bid is accepted
c) To provide financial security in case the contractor withdraws their bid
d) To secure funds for the project

View Answer

Answer: c) To provide financial security in case the contractor withdraws their bid
Explanation: A bid bond is a form of financial security provided by the contractor to the client to ensure that the contractor will proceed with the project if their bid is accepted.

What is the primary purpose of a theodolite in engineering surveying?

a) Measuring horizontal angles
b) Measuring distances between survey points
c) Determining elevations
d) Establishing a reference point for the survey

View Answer

Answer: a) Measuring horizontal angles
Explanation: Theodolites are used to measure horizontal and vertical angles in engineering surveying.

Which surveying method is commonly used to measure large areas of land and establish a network of control points?

a) Topographic surveying
b) Geodetic surveying
c) Cadastral surveying
d) Hydrographic surveying

View Answer

Answer: b) Geodetic surveying
Explanation: Geodetic surveying involves measuring large areas of the Earth’s surface to establish control points for other surveys.

In surveying, what does the term “benchmark” refer to?

a) A device used to measure angles
b) A known elevation point used as a reference for other elevations
c) A type of levelling instrument
d) A tool used to measure distances

View Answer

Answer: b) A known elevation point used as a reference for other elevations
Explanation: A benchmark is a point of known elevation used as a reference for determining the elevations of other points during a survey.

Which surveying technique involves measuring angles and distances from two known points to determine the position of an unknown point?

a) Trilateration
b) Triangulation
c) Resection
d) Leveling

View Answer

Answer: b) Triangulation
Explanation: Triangulation involves measuring angles and distances from two known points to determine the location of an unknown point.

What is the purpose of leveling in engineering surveying?

a) To measure horizontal angles
b) To determine the position of survey points
c) To establish a network of control points
d) To measure vertical elevations

View Answer

Answer: d) To measure vertical elevations
Explanation: Leveling is used to measure the vertical elevation differences between different points on the ground.

Which surveying method is used to measure the elevations of points on the Earth’s surface relative to a reference point?

a) Traverse surveying
b) Photogrammetry
c) Tacheometry
d) Leveling

View Answer

Answer: d) Leveling
Explanation: Leveling is a surveying method used to determine the height or elevation of points on the Earth’s surface relative to a reference point.

Which material is commonly used as a reinforcement in reinforced concrete structures?

a) Aluminum
b) Steel
c) Copper
d) Timber

View Answer

Answer: b) Steel
Explanation: Steel is commonly used as a reinforcement in reinforced concrete structures to improve their tensile strength.

What is the primary ingredient in Portland cement, the most common type of cement used in construction?

a) Limestone
b) Silica
c) Gypsum
d) Clay

View Answer

Answer: a) Limestone
Explanation: Limestone is the primary ingredient in Portland cement, which is widely used in construction.